High voltage isolation

Industry partnersPermitsHigh voltage isolation

If you are doing work that needs power to be isolated to our electricity distribution network, then you need to arrange a high-voltage isolation.

Planning switching instructions to isolate work is a complex process which requires coordination across our network control centre and all forms of project and field teams active in the vicinity of the planned works.

You can arrange a high-voltage isolation by completing the form below.

 

How long does it take to arrange a high-voltage isolation?

  • We require a minimum of 8 weeks notice to be able to fulfill your request
  • Payment must be made before isolation date

What you need to complete this application

  • Applicant information
  • Customer information (for billing purposes)
  • Site address
  • Detailed information regarding purpose for isolation
  • Description of any prescribed works undertaken by a Registered Electrical Contractor (REC)
  • Preferred date and date of isolation
  • Preferred date and date of reconnection
  • Internal reference number (if required)
  • Any attachments as necessary

High voltage isolation form

Max. filesize 3MB. Please upload only pdf, doc, docx, xls, xslx, pages, numbers, jpg, tiff, bmp, png, txt, csv, rtf, odt or ods files. Note that if form submission fails, please re-upload attachment.

Your details

Your NMI number appears on the bill you receive from your retailer
question mark icon

Looking for something else in
Permits

Explore another page